Setting the schedule

Schedule a reporting job to occur once or on a repeating cycle on the Schedule Report tab of the page Presentation Reports > Scheduler.

Note: It is advisable to schedule report jobs on different days or at different times, to avoid overloading the Log Database and slowing performance for logging and interactive reporting.

Steps

  1. Enter a name that uniquely identifies this scheduled job in the Job name field.
  2. Select Recurrence Options for the job based on the Recurrence Pattern you want, as follows:
    Recurrence Pattern Recurrence Options
    Once Enter the exact date on which to run the job, or click the icon to select from a calendar.
    Daily No additional recurrence options are available.
    Weekly Mark the check box for each day of the week the job is to run.
    Monthly

    Enter the dates during the month for running the job. Dates must be a number between 1 and 31, and must be separated by commas (1,10,20).

    To run the job on consecutive dates each month, enter a start and end date separated by a hyphen (3-5).

  3. In the Schedule Time box, set the start time for running the job.

    The job begins according to the time on the email appliance.

    Note: To start generating the scheduled reports today, select a time late enough that you can complete the job definition before the start time.
  4. In the Schedule Period box, select a date for starting the job. Options for ending the job are as follows:
    No end date

    The job continues to run indefinitely, according to the established schedule.

    To discontinue the job at some time in the future, either edit or delete the job. See Viewing the scheduled jobs list.

    End after Select the number of times to run the job. After that number of occurrences, the job does not run again, but it stays in the Job Queue until you delete it. See Viewing the scheduled jobs list.
    End by Set the date when the job stops running. It does not run on or after this date.